  1. Increase housing on the reservation and increasing capacity to document a lack of housing through surveys and inspections.
  2. Energy efficiency and residential energy audits
  3. EV Chargers, Infrastructure + Fleet Planning, and Job Training
  4. Solar and EV master plan
  5. Provide affordable and resilient power to the Chemehuevi community
    1. Increase energy storage systems
      • Back-up power and long duration energy storage
      • Pumped hydro, previous talks with Department of Energy
      • Microgrids, 5MW microgrid system to gain independence from SCE
    2. Large-scale power generation
      • 2000 acres of solar – 200 MW
      • Previous developer backed out
      • Long distance to larger transmission (5-7 miles)
    3. Interconnection support
      • Challenges with interconnection, rights of way/easements, CAISO, substation access
        • Substation/Power station is on adjacent non-Tribal land
      • The eservation has 1 main line that comes into the casino then through different roads and finally the housing community (which is on a loop system)
      • Work with SCE to relocate lines
    4. Smaller-scale power generation
      • A 30-50 acre solar grid system to connect to the casino to provide direct power reduction
  6. Energy ordinance is established, but the Tribe is interested in a Tribal Utility
    1. WAPA credit allocations, Hoover Dam
    2. Previous BIA Tribal energy development and capacity grant
    3. A Joint Powers Agency with Chemehuevi (Tribal Power Exchange)
      • This involves offloading directly with the casino and billing back at a 90% rate, allowing those funds to build an energy projects fund.
  7. Metropolitan Water District easement